In this test there is a sudden breakdown of the insulation between about 5 6 and 6 5kv and the test is shut down at the end of step 7 at about 6500v because the acceleration in the measured current exceeded the roc limit from step 6 to step 7.
Step voltage test electric motors.
The dc voltage is applied to all three phases of the winding and raised slowly to a preprogrammed voltage step level and held for a predetermined time period.
Experience is the best teacher in setting up the scheduled periods for your equipment.
For example for a 1500 v ac voltage the equivalent dc voltage to produce the same amount of stress on the insulation would be 1500 x 1 414 or 2121 v dc.
From these ones it has evolved a test that implementing the high voltage d c.
How to check an electric motor.
With the motor running check the running amps of the motor using clamp on meter.
A motor placed in storage may or may not work regardless of its physical appearance.
Electric motor testing is usuallly the first thing to be sacrificed when cutting back on operational expenses.
When a motor fails it is often difficult to see why it failed just by looking at it.
A quick check out can be done with.
Dc step voltage test it is typically performed at twice line voltage plus 1000 volts.
The test allows the technician to observe how the insulation system responds to an over voltage stress.
Step voltage test has become an industrial standard in common use for field testing.
This article describes how the machine s insulation is tested and the information.
Ieee 43 2000 ieee 95 2002.
The test voltages governed by ieee are reflected in table ii.
The leakage current is.
Therefore if we use dc test voltage we ensure that the dc test voltage is under root 2 or 1 414 times the ac test voltage so the value of the dc voltage is equal to the ac voltage peaks.
4160v motor test voltage 9320v.
As the voltage is.
Minimum test value of the electric motor is 1 meg ohm 1 mω.
But smart companies understands is that what this means for maintenance programs is billions of dollars of lost revenue through increased motor repair costs downtime and waste in industrial and commercial companies.
You should make these periodic tests in the same way each time.
Pump motor or a short control cable may be vital to a process in your plant.
As the step voltage test progresses every 60 seconds the voltage applied to the insulation system is increased in specific voltage increments which is determined by the user.
The first ones ieee 62 1958 eda test basis to the late ones.
The step voltage test is performed upon completi on of a successful polarization index pi test starting at the same voltage used for the pi test.
Match up to the full load.
The standard procedure is to increase voltage in one minute increments.
Step voltage test the step voltage test records the peak in rush and decay of current as each increase step in dc voltage is applied to the circuit.